What Changed
- Hong Kong SAR currently maintains 29 concrete batching plants holding Specified Process Licences across nine districts under the Air Pollution Control Ordinance (Cap. 311).
- The site of the Kwok Shui Road plant was rezoned to 'Residential (Group E)' around 20 years ago, with building plans for residential redevelopment approved by the Buildings Department in 2016 and 2024.
- A 2021 study by the Civil Engineering and Development Department determined that public housing completion planned for 2030-2031 near the plant is technically feasible, incorporating road widening of Kwok Shui Road from 7.3m to 9.5m.
### Background and Regional Operational Context
On November 25, 2026, the Acting Secretary for Development of the Hong Kong Special Administrative Region (Hong Kong SAR), Mr David Lam, provided a written reply to Legislative Council Question 14 (LCQ14) raised by the Hon Kwok Fu-yung. The parliamentary inquiry focused on public concerns regarding a concrete batching plant (CBP) operating on Kwok Shui Road in Tsuen Wan, specifically addressing vehicle traffic, road safety, environmental hygiene, and the plant's proximity to a planned public housing project expected to be completed in 2030–2031.
In Hong Kong SAR, concrete serves as an essential construction material. Because freshly mixed concrete hardens rapidly, it requires prompt delivery to active construction sites to maintain material quality. Consequently, the government maintains a regional distribution of CBPs across nine districts. Currently, 29 CBPs operate across Hong Kong SAR under Specified Process Licences (SPLs) issued by the Environmental Protection Department (EPD).
### Statutory Environmental Control Framework
The operation of any CBP within Hong Kong SAR requires compliance with multiple statutory frameworks administered by environmental authorities:
1. **Air Pollution Control Ordinance (Cap. 311):** The EPD issues and renews SPLs under Cap. 311 to control air pollutant emissions. Licence holders must use the best practicable means at all times to prevent air pollutant emissions, refrain from inhibiting the attainment or maintenance of air quality objectives, and prevent noxious or offensive emissions or nuisances. Applicants must demonstrate their capability to operate effective dust control measures and may be required to install enhanced monitoring systems for real-time surveillance of polluting processes.
2. **Noise Control Ordinance and Water Pollution Control Ordinance:** Beyond air quality, CBPs must avoid excessive noise emissions and refrain from illegal wastewater discharges. The EPD conducts periodic site inspections and takes statutory enforcement actions when non-compliance occurs.
### Land Use Planning and Redevelopment Framework in Tsuen Wan
From a land use planning perspective, CBPs may operate in areas designated as "Industrial" zones subject to planning permission. To facilitate the transition of the Kwok Shui Road traditional industrial area into a residential neighbourhood, the Town Planning Board approved the rezoning of approximately 3.83 hectares—encompassing the subject CBP and adjoining industrial premises—from "Industrial" to "Residential (Group E)" approximately 20 years ago.
Because the subject CBP existed prior to the rezoning, it is tolerated as a pre-existing industrial use. However, the Planning Department prohibits new industrial developments on the site to prevent further incompatibility with surrounding residential areas. Transformation of the surrounding area has proceeded incrementally, with two nearby industrial sites redeveloped into residential projects in 2010 (Primrose Hill) and 2014 (The Rise).
Regarding the specific CBP site on Kwok Shui Road:
- In 2011, the Town Planning Board granted planning permission to the private lot owner for residential development.
- The Buildings Department approved building plans for residential developments on the site in 2016 and 2024.
- Because the land is privately owned, the timing and execution of any residential redevelopment depend on the private commercial decision of the lot owner.
### Environmental and Traffic Impact Assessments for Nearby Public Housing
The government plans to develop public housing on the former site of Kwai Chung Public School along Kwok Shui Road, targeted for completion in 2030–2031. In 2021, the Civil Engineering and Development Department (CEDD) completed a feasibility study that incorporated an Environmental Review (ER) and a Traffic Impact Assessment (TIA) to evaluate potential operational impacts from the nearby CBP:
- **Environmental Assessment:** The ER concluded that the CBP would not cause adverse environmental impacts on future residents of the public housing development.
- **Traffic Assessment and Mitigation:** The TIA recommended widening a section of Kwok Shui Road from its existing width of approximately 7.3 metres to approximately 9.5 metres. This expansion ensures sufficient capacity for two-way traffic flow even when vehicles are temporarily parked along the road segment.
- **Planning Approval:** In 2022, the Town Planning Board took these assessment findings into consideration when approving the rezoning of the housing site from "Government, Institution or Community" to "Residential (Group A) 21".
### Frequently Asked Questions
**Question 1: How many concrete batching plants are currently licensed to operate in Hong Kong SAR, and under what mechanism are they regulated?**
*Answer:* A total of 29 concrete batching plants currently hold Specified Process Licences (SPLs) issued by the Environmental Protection Department across nine districts in Hong Kong SAR. Their air emissions are regulated under the Air Pollution Control Ordinance (Cap. 311), while their operations must also strictly comply with the Noise Control Ordinance and the Water Pollution Control Ordinance.
**Question 2: Why is the concrete batching plant on Kwok Shui Road permitted to operate near residential areas?**
*Answer:* The plant represents an industrial use that existed before the Town Planning Board rezoned the 3.83-hectare area from "Industrial" to "Residential (Group E)" approximately 20 years ago. As a pre-existing use, it is tolerated under planning rules, though no new industrial developments are permitted on the site.
**Question 3: Has planning permission been granted for the redevelopment of the Kwok Shui Road concrete batching plant site?**
*Answer:* Yes. The Town Planning Board granted planning permission for residential development on the lot in 2011, and the Buildings Department approved building plans for residential development on the site in 2016 and 2024. However, implementation remains subject to the private lot owner's commercial decision.
**Question 4: What mitigation measures are planned to handle traffic generated near the proposed public housing site on Kwok Shui Road?**
*Answer:* Based on the Civil Engineering and Development Department's 2021 Traffic Impact Assessment, a section of Kwok Shui Road will be widened from approximately 7.3 metres to approximately 9.5 metres to preserve two-way traffic flow, even during temporary vehicle parking.
Who May Be Affected
Residents of Tsuen Wan District, future tenants of the planned Kwok Shui Road public housing project, operators of concrete batching plants, land developers, and environmental/planning regulators in Hong Kong SAR.
Cross-Border Context
Not applicable / None provided in source text.
What to check next
- Annex to LCQ14 detailing individual lease terms and licence expiry dates for all 29 CBPs.
- Future notices from the Buildings Department or private lot owner regarding redevelopment progress on the Kwok Shui Road CBP site.